Chinese firm seeks PKR 12.35 bn dues from Pakistan energy ministry

Περισσότερα Νέα

- Advertisement -

A state-owned Chinese firm registered in Pakistan has expressed concern over delay in their payment and asked the Pakistan Ministry of Energy (power division) to release Pakistani Rupees (PKR) 12.35 billion as Transmission Service Payment.

The China Electric Power Equipment and Technology Co Ltd (CET), registered in Pakistan as Pak Matiari-Lahore Transmission Company Private Limited (PMLTC), has expressed their concern at this issue. The companies also asked the ministry to prioritise this issue, Pakistani newspaper Dawn reported on Wednesday.

But National Transmission & Despatch Company (NTDC), on other hand, claimed that no payment is pending on its part.

In a recent letter to energy minister Hammad Azhar, the company explains that it has received the TSP for September to November 2021 and a partial payment of 19.46 per cent for the month of December 2021.

It also informs the minister that in accordance with the Transmission Service Agreement (TSA), by the beginning of March 2022, the companies should have received the TSP from September 2021 to February 2022 along with payment for adjustment of indexation.

- Advertisement -

Moreover, the TSP for the pre-CoD (commercial operation date) period that remained pending is at PKR 21.1 billion, while the payment company received so far is PKR 8.75 billion which amounts to 41.4 per cent of the total amount it billed, according to Dawn.

The letter also reads, “We need to stress again that the total amount of invoices we billed NTDC is PKR 21.21bn, out of which, after receipt of PKR 8.75 billion, the unpaid amount is PKR 12.35bn.”

The company also demanded the clearance of the amount before March 24 since the approval of foreign exchange conversion from the State Bank of Pakistan for making payment to the lender takes time.

“This issue emerged before my appointment as Managing Director. However, we always give priority to such payments. And we did,” NDTC MD was quoted as saying by Dawn. (ANI)

This report is auto-generated from ANI news service. ThePrint holds no responsibility for its content.

- Advertisement -

Ροή ειδήσεων

ΣΧΕΤΙΚΑ ΑΡΘΡΑ

How Japan built a rare earth supply chain without China

As the United States and other nations scramble to secure rare earths outside China and build up their domestic supplies, Japan’s experience provides lessons...

Human rights?

In a message on the occasion of International Human Rights Day which fell yesterday (December 10), Prime Minister Muhammad Shehbaz Sharif reaffirmed Pakistan’s resolve...

UK clamps down on China-based companies for reckless and irresponsible activity in cyberspace

Two tech companies based in China have been sanctioned for reckless and indiscriminate cyberattacks UK exposes two China-based companies that have carried out cyberattacks against...

See how a Chinese invasion of Taiwan could unfold

Five miles off Taiwan’s coast, ZTD-05 amphibious vehicles roll out of ships and zip over the water amid a hail of artillery fire. The...

ΔΗΜΟΦΙΛΗ ΑΡΘΡΑ

Oι παραβιάσεις των ανθρωπίνων δικαιωμάτων στο Πακιστάν

Σε μήνυμά του με την ευκαιρία της Παγκόσμιας Ημέρας Ανθρωπίνων Δικαιωμάτων που εορτάστηκε χθες (10 Δεκεμβρίου), ο πρωθυπουργός Μουχάμαντ Σεχμπάζ Σαρίφ επιβεβαίωσε την αποφασιστικότητα...

Πώς η Ιαπωνία έχτισε μια αλυσίδα εφοδιασμού σπάνιων γαιών χωρίς την Κίνα

Καθώς οι Ηνωμένες Πολιτείες και άλλα έθνη αγωνίζονται να εξασφαλίσουν σπάνιες γαίες εκτός Κίνας και να αυξήσουν τις εγχώριες προμήθειές τους, η εμπειρία της...

How Japan built a rare earth supply chain without China

As the United States and other nations scramble to secure rare earths outside China and build up their domestic supplies, Japan’s experience provides lessons...

Human rights?

In a message on the occasion of International Human Rights Day which fell yesterday (December 10), Prime Minister Muhammad Shehbaz Sharif reaffirmed Pakistan’s resolve...